A checklist for airside and waterside equipment: relevant nameplate fields, locations, access constraints and the system connections to verify.

On every HVAC unit capture make, model, serial, capacity, electrical rating, refrigerant where applicable, location and condition. Then establish the relationships while on site: which unit serves which zones, which drive runs which motor, and which loop feeds which coil. The ratings can be read from a plate later; the relationships usually cannot.

AIRSIDEAHU / RTUCFM · ESPFANSCFM · HPTERMINALSMIN / MAX CFMCOILSMBHWATERSIDECHILLERSTONS · kW/TONBOILERSMBH · EFFPUMPSGPM · HEADTOWERSTONS · GPM

Airside plant

  • 01: Air handling unit

  • 02: Rooftop unit

  • 03: Fan coil unit

  • 04: VAV / terminal box

  • 05: Exhaust fan

Waterside plant

  • 01: Chiller

  • 02: Boiler

  • 03: Pump

  • 04: Cooling tower

  • 05: Heat exchanger

Relationships to establish on site

Follow the distribution

Read the labels that already exist

Refrigerant, age and the replacement clock

Age and refrigerant type support replacement planning alongside condition, maintenance history and system needs. Record a printed manufacture date or the basis for an age estimate. Review refrigerant availability and current requirements when planning work.

Capturing both at survey time means the capital plan can be sorted by exposure as well as by age, without going back to read plates that were already photographed once.

Access is part of the data

On HVAC surveys the constraint that decides project cost is frequently physical: a chiller that cannot leave the plant room without removing a wall, a rooftop unit whose crane position blocks the only service road, a fan coil above a hard ceiling in an occupied tenant space.

Record it while you are there. Curb sizes, door and riser dimensions, access routes and rigging constraints belong in the survey, because they are the fields nobody thinks to capture and everybody needs later. The general equipment checklist covers the fields common to all disciplines.

Using the HVAC list

What should be captured on a rooftop unit?

Manufacturer, model and serial from the main plate; cooling capacity in tons; heating input and output; refrigerant type and factory charge; MCA and MOCP; supply fan motor rating; and the economiser arrangement. Add the curb dimensions and the roof access route, because both decide what a replacement actually costs.

How do you keep a large terminal-unit survey organized?

Use a consistent route and capture standard: tag, location, nameplate and relevant airflow or reheat information. Confirm proposed connections against available plans and observations. Survey duration still depends on equipment count and access.

Is refrigerant worth recording if the equipment is working fine?

Yes. Record the refrigerant type and nameplate charge for servicing and replacement planning, alongside age, condition and maintenance history. Check current requirements and availability when making a replacement decision.